UK SRSThe UK Sustainability Reporting Standards, ESOS, SECR and TCFD, read against the published text.HUBUK SRS GuideAn independent reference guide to UK SRS, ESG, TCFD, SECR, ESOS and the global standards.Global Reporting StandardsSustainability reporting standards worldwide: ISSB, the EU CSRD after Omnibus I, California SB 253 and SB 261, and UK SRS.UK SRS StandardsUK SRS S1 and S2 at the provision: reliefs, comply or explain, and the FCA statements.ESOS QuestESOS Phase 4 in depth: qualification, the audit, sign-off, action plans and penalties, read against the Regulations.YOU ARE HERESRS EngineeringThe data build behind a UK SRS report: metrics, owners, controls and timing.SRS ReportWhat a UK SRS report contains, how it is assembled, and how to read one.UK SRS ReportAnalysis and commentary: CDP, the DESNZ emission factors, SECR and ESOS, with every figure cited.UK SRS NewsThe cluster's news publication, and what a UK SRS report contains.UK SRS DeliveryTemplates, costs, ESOS delivery guides and readiness assessment.UK SRS FinanceFinanced emissions, PCAF and IFRS S1/S2 for banks, insurers and asset managers.SECRStreamlined Energy and Carbon Reporting: deadlines, thresholds, eligibility and guidance.Carbon CreditsCarbon credit ratings, risk analysis, valuation and market structure.Environmental RegimesThe eight UK environmental reporting regimes, their thresholds, deadlines and regulators.UK SRS ServicesThe services arm: ESOS, SECR, net zero and sustainability consultancy.

ESOS Phase 4 · Schedule 1

ESOS Phase 4 qualification: the large undertaking test

Whether an organisation is in ESOS Phase 4 is settled on a single day, 31 December 2026, by a test in Schedule 1 of the Regulations.

The test is short, but its wording, its group rule and its exclusions catch organisations out.

Tool · nothing is stored or sent

Four questions, one answer

The tree follows the order the Regulations apply the test.

Insolvency is asked first because it removes an undertaking that would otherwise qualify.

The group question comes last because it can bring in an undertaking that is small on its own figures.

ESOS Phase 4 qualification
Was the undertaking subject to insolvency proceedings at any point between 31 Dec 2026 and 5 Dec 2027?
Reg 16 as amended by SI 2026/701 reg 6

The wording

“At least” and “in excess of” are not the same

The employee limb is inclusive: 250 qualifies.

The money limbs are exclusive: a turnover of exactly £44 million does not.

And the money test needs both turnover and balance sheet over their limits at once.

The Environment Agency’s Phase 4 guidance restates the test; the wording that decides a borderline case is the Schedule’s.

Worked from SI 2014/1643 Sch 1 ¶¶1, 1A; illustrative figures.
Figures on 31 Dec 2026Large?Why
250 employeesYesAt least 250
249 employees, £45m turnover, £39m balance sheetYesBoth money limbs exceeded
249 employees, £60m turnover, £30m balance sheetNoBalance sheet not exceeded
100 employees, £44m turnover, £50m balance sheetNo£44m is not in excess of £44m

Groups

One large company brings in the group

ESOS looks at UK groups, not single companies.

Where any UK undertaking in a group is large, every UK undertaking in that group participates, however small it is.

The group normally notifies as one participant through a responsible undertaking, usually the highest UK parent.

An overseas parent does not itself participate, but its UK subsidiaries are tested and grouped under the same rule.

Snapshot, not average

Status on 31 December 2026 decides Phase 4, so an acquisition or disposal in 2027 does not change who must notify by 5 December 2027.

Exclusions and geography

Who is out, and who regulates who is in

SI 2026/701 widened the insolvency exclusion to proceedings at any point between the qualification date and the compliance date.

ESOS covers England, Wales, Scotland, Northern Ireland and offshore activities.

The regulator follows the registered office under regulation 6, and the Environment Agency administers the scheme for the whole UK.

Thresholds were not aligned with SECR in Phase 4; ESOS and SECR remain separate tests.

Once in, the next step is the lead assessor and sign-off, and the family’s ESOS Phase 4 compliance guide on uksrs.org.uk covers every duty that follows.

Frequently asked

Questions people ask

What is the ESOS Phase 4 qualification date?

31 December 2026.

Regulation 4(3)(b) makes the qualification date the 31 December immediately before the compliance date, which for Phase 4 is 5 December 2027.

What are the ESOS qualification criteria?

An undertaking is large if it employs at least 250 persons, or has an annual turnover in excess of £44 million and an annual balance sheet total in excess of £38 million.

Both money limbs must be exceeded together.

Does a whole group have to comply with ESOS?

Yes.

If any UK undertaking in a group is a large undertaking, the UK group participates as a whole, with one responsible undertaking notifying for it unless the group agrees to split.

What if our size changes after 31 December 2026?

It makes no difference to Phase 4.

Status on the qualification date governs, so an undertaking that qualified must comply by 5 December 2027 even if it shrinks, and one that grows afterwards waits for the next qualification date, 31 December 2030.

Are insolvent companies excluded from ESOS?

Yes.

SI 2026/701 widened the exclusion to undertakings subject to insolvency proceedings at any point between the qualification date and the compliance date, and to group undertakings of an insolvent large undertaking.

Does ESOS apply in Scotland and Northern Ireland?

Yes.

ESOS applies across the UK and to offshore activities.

The compliance body follows the registered office: the Environment Agency in England, Natural Resources Wales, SEPA in Scotland, the Northern Ireland regulator, and the Secretary of State for activities wholly or mainly offshore.

Sources

Primary sources

Every figure, date and status on this page traces to the instrument’s owner.

Secondary commentary is never the source for a number.

Checked against 11 sources fromlegislation.gov.ukEnvironment AgencyEnvironment Agency / GOV.UK
  1. legislation.gov.uk
    SI 2014/1643 Schedule 1 — the large undertaking test and amounts A and B

    At least 250 employees, or turnover in excess of £44m and balance sheet in excess of £38m.

  2. legislation.gov.uk
    SI 2014/1643 regulation 4 — compliance periods, qualification and compliance dates

    Generates 6 Dec 2023 – 5 Dec 2027, 31 Dec 2026 and 5 Dec 2027.

  3. legislation.gov.uk
    The Energy Savings Opportunity Scheme Regulations 2014 (SI 2014/1643)

    The scheme itself. The consolidated text does not yet show the 2026 amendments.

  4. legislation.gov.uk
    The Energy Savings Opportunity Scheme (Amendment) Regulations 2026 (SI 2026/701), in force 22 July 2026

    Every Phase 4 change: routes, savings reporting, the action plan review, the third progress update.

  5. legislation.gov.uk
    SI 2026/701 — Explanatory Note

    The government’s own summary of what the 2026 amendments do.

  6. legislation.gov.uk
    SI 2014/1643 regulation 6 — the compliance bodies

    Which regulator a participant answers to.

  7. Environment Agency
    How to comply with the Energy Savings Opportunity Scheme (ESOS) phase 4 (30 July 2026)

    The regulator’s guidance; a restatement of the Regulations, never the master.

  8. Environment Agency
    Comply with the Energy Savings Opportunity Scheme (ESOS) phase 4 — publication page

    Published 30 July 2026.

  9. Environment Agency
    ESOS phase 4 guidance, Appendix C — advice for complying with ESOS

    Practical notes, including participants in other schemes.

  10. Environment Agency / GOV.UK
    Energy savings opportunity scheme (ESOS): find out if you qualify and how to comply (updated 2 September 2026)

    The GOV.UK hub, now a Phase 4 page, and the approved lead assessor register list.

  11. legislation.gov.uk
    The Companies (Directors’ Report) and Limited Liability Partnerships (Energy and Carbon Report) Regulations 2018 (SI 2018/1155)

    SECR — a separate, annual regime; ESOS thresholds were not aligned with it in Phase 4.